BHP Neil Simpson 1 Plant Demolition

The Neil Simpson Plant was the third of four (4) power plants that were awarded to Independence Demolition. All four plants included complete environmental decommissioning, demolition, removal and site restoration.

This site specifically included demolition of approximately 1,950 GT of structures and equipment. The environmental scope of work included asbestos abatement, removal of all universal wastes and fly ash / coal residuals, lead & mercury abatement, a 10,000 gallon fuel oil above ground tank, and draining of all oils. Final site restoration included fill placement for all site pits and basements.

Contact

  • West
    Aurora, CO
    (720) 437-8862
  • Midwest Headquarters
    Brecksville, OH
    (216) 446-3400
  • South Atlantic
    Orlando, FL
    (407) 816-6160
  • Mid-Atlantic
    Sterling, VA
    (703) 430-1005
  • East
    Cheswick, PA
    (412) 767-9800
Maps & Directions
© 2024 Independence Demolition
A Division of Independence Excavating, Inc
Privacy Policy