Progressive Field Renovations
The project consisted of several areas of selective demolition to allow for new construction. The work mainly took place in the center field patio and seating area, right field mezzanine seating areas as well as all three levels of the right field suites. The work in center field included removal of the overhead pedestrian bridge and all the concessions and patio areas to allow modifications to gate C entrance. The seating removals in center field allowed for the re-working of both bullpens A large portion of the right field mezzanine seating was removed to make room for the new Kids Club area while the suites near the right field foul pole were gutted and portions removed to allow for the new construction of the two-level restaurant/bar area. The demolition work needed to be completed in approximately one month in order to allow the renovations to be completed prior to the 2015 baseball season.